(ĐN)- Vice Chairman of Dong Nai provincial People’s Committee Ho Van Ha chaired a meeting to review the progress of social housing projects. According to the Department of Construction, the province plans to start construction on over 9,800 units and complete approximately 2,047 units in 2025.
ADVERTISEMENT
![]() |
Vice Chairman Ho Van Ha speaks at the meeting |
Currently, 10 ongoing and new projects with a total scale of 13,000 units have investors; 7 projects (8,000 units) are in the investor selection phase, while 8 projects (11,000 units) lack investment approval.
Key projects expected to deliver housing in 2025 include worker housing in Trang Bom District and social housing in Phuoc Tan Ward, Bien Hoa City.
ADVERTISEMENT
Challenges include 12 projects awaiting approval from the Provincial People's Council, 3 projects not yet listed for bidding, planning adjustment issues, and delays in investment approval for projects on 20% of commercial land.
Vice Chairman Ha emphasized meeting both targets: initiating construction on 9,800+ units and completing over 2,000 units. The Department of Planning and Investment was tasked with expediting investor selection for 7 approved projects and preparing for investment certificate ceremonies. For the 8 pending projects, proposal evaluations should be fast-tracked.
ADVERTISEMENT
Additionally, the Department of Construction will assign specific housing targets to localities and host a conference to attract private infrastructure investment. All departments were instructed to cut administrative processing time by 50% (except for procedures with fixed legal timelines) and provide maximum support to developers.
Reported by H.Loc